The principal mistake usually occurs after the first missed deadline. The buyer agrees to wait, but revised delivery dates remain confined to telephone conversations. The original deadline is recorded in the contract, while the parties’ subsequent conduct becomes open to conflicting interpretations. The supplier argues that the deadline was extended, whereas the buyer believes that it merely refrained temporarily from commencing court proceedings.
Every extension should therefore be documented in writing, including the revised deadline, whether it is final, and the consequences of a further breach. If the buyer is no longer interested in receiving the goods, this must also be stated unequivocally. A buyer cannot continue demanding delivery for several months and then assume that the repayment obligation arose retroactively. The monetary claim must be properly established: the buyer must state the remedy it has selected, demand repayment, and set a deadline where the contract does not already provide one.
The second mistake is investigating the debtor too late. If the supplier’s bank accounts are empty, its real estate has been transferred, and bankruptcy proceedings have already been opened by the time the claim is filed, even indisputable documents will not guarantee actual recovery. A Ukrainian counterparty should therefore be investigated before court proceedings are commenced and, ideally, before the commercial relationship begins.
The third mistake is attempting to include every possible additional amount in the claim without verifying its legal basis. Repayment of the advance, contractual penalties, interest, inflation adjustment, and damages have different legal characteristics. An overstated calculation complicates the case, increases the court fee, and gives the defendant additional grounds for objection. A strong position is based not on the highest possible figure, but on an amount that can be substantiated consistently through documents and applicable law.